Brand new rail from Corus, manufactured a few weeks ago. |
Track was soon laid under the B4632 road bridge. The bridge team were putting up new fencing on the right. |
Oops - Mr Lees won't want to take the train over this joint ! Time for some packing. This rail is so new it still has a bar code on it ! |
Temporary clamps help us get the works train over bad joints. These will be welded soon. |
First 'passengers' under the B4632 road bridge |
Around 10 panels laid, Stanton Fields road bridge in distance getting closer. Beyond this the two Dave's were clearing the undergrowth. |
The P.Way train was exceptionally long today, containing ballast wagons, flat wagons of sleepers, tools and mess coach. |
Looking north from the B4632 road bridge, the other end of the P.Way train... |